Search
Beach Drive Construction Update No.4
Posted on Friday, July 18, 2025 02:18 PM
Work Completed This Week Construction Update
- Continued to install hoarding fence along Beach Drive from Spruce Street to 2nd Street
- We continued to remove existing infrastructure on Main Street, Spruce Street and Beach Drive
- Crews began installing the dewatering system and installed dewatering well points to address ground conditions for the upcoming pipe installation
- We installed wayfinding signage on the fence to help residents and visitors navigate to the beach and local businesses
- Infrastructure...
Beach Drive Construction Update No.3
Posted on Thursday, July 17, 2025 03:47 PM
Work Completed This Week Construction Update
- Installation of hoarding fence continued along Beach Drive from Spruce Street to 2nd Street
- Removals of existing infrastructure continued on Main Street and Beach Drive
- Removals began on Spruce Street at Main Street
- Infrastructure Investigation throughout project limits
- Installation of wayfinding signs to help the public identify where they are, beach access points, and businesses open for business.
Working Coming Up Next Week
- Continuation of hoarding fence...
Beach Drive Construction Update No.2
Posted on Friday, July 04, 2025 03:05 PM
Work Completed This Week Construction Update
- Installed traffic control measures and signs. Beach Drive is now closed between Spruce Street and 2nd Street.
- Pedestrian fencing has been installed along Main Street, Beach Drive, and 1st Street. Sidewalks remain open for businesses and beach access.
- Began installing hoarding fence along Beach Drive.
- Started to remove existing infrastructure on Main Street and Beach Drive.
- Continued to move equipment and materials to the site this week.
- Continued...
Beach Drive Construction Update No.1
Posted on Tuesday, June 24, 2025 01:22 PM
Welcome to our first update on Beach Drive construction.
Construction Update
- This week, crews are organizing and moving equipment and materials around, getting ready to put shovels in the ground.
- We’re getting ready to install traffic control and other signage.
- We’re going to be closing Beach Drive between Spruce St. and 2nd Street N.
- We will begin to install hoarding fencing along Beach Drive, and pedestrian fencing of the work area will begin.
- We’re completing infrastructure investigations at Main...
Public Notice: Transit Master Plan
Posted on Tuesday, June 17, 2025 02:56 PM
We want to hear from you!
The Town of Wasaga Beach is currently developing a 10-year Transit Master Plan. As part of the development of this plan, we want to hear directly from the community.
We are seeking input from the community to better understand the transportation experiences in Wasaga Beach and learn more about your travel needs and experience with the existing transit services, as well as get your input on future priorities and options for Wasaga Beach Transit. We encourage you to share...