Road Closure - Pauline Drive
Posted on Tuesday, November 07, 2023 11:51 AM
Please be advised of a temporary road closure of Pauline Drive, between River Road West and Edgewater Road, as part of the capital works River Road West Reconstruction project (PW2023-15)
Location: Pauline Drive
Nature of Construction: To facilitate the installation of Storm & Sanitary Structures/Pipes
Date of Temporary Closure: November 7th to December 15th, 2023
Estimated Time of Closure: 7:00am Tuesday November 7th to Friday December 15th 5:00pm
Contractor: Green Infrastructure Partners (GIP)
Contact...
DATE OF INTERRUPTION - #9035 & #9031 Beachwood Road, west of Constance Boulevard
Posted on Monday, November 06, 2023 02:58 PM
DATE OF INTERRUPTION: Wednesday November 8th, 2023
TIME OF INTERRUPTION: 9:00am to 5:00pm
LOCATION: #9035 & #9031 Beachwood Road, west of Constance Boulevard
As part of the capital works project, West End Watermain Looping Beachwood Road (CONTRACT No. PW-2018-08), Arnott Construction will be completing work on the existing watermain. During the above noted times, water will not be available. It is advised that residents who receive a notice properly prepare for the shut down by filling pots or jugs...
DATE OF INTERRUPTION - Middlebrook Road, William Avenue, James Avenue, and Jack Street
Posted on Monday, November 06, 2023 02:55 PM
DATE OF INTERRUPTION: Tuesday November 7th, 2023
TIME OF INTERRUPTION: 9:00am to 5:00pm
LOCATION: Middlebrook Road, William Avenue, James Avenue, and Jack Street
As part of the capital works project, West End Watermain Looping Beachwood Road (CONTRACT No. PW-2018-08), Arnott Construction will be completing work on the existing watermain. During the above noted times, water will not be available. It is advised that residents who receive a notice properly prepare for the shut down by filling pots or...
NOTICE OF CONSTRUCTION-West End Watermain Looping Beachwood Road
Posted on Thursday, September 21, 2023 04:11 PM
Please be advised that the construction project for the West End Watermain Looping, on Beachwood Road, is scheduled to commence on September 18th, weather permitting. Work is expected to be completed during the times of 7am – 6pm (Daily Monday to Friday) and project completion estimated to be November 30th. The works will include installation of watermain and sanitary sewer, installation of sanitary and watermain services, and clearing of existing trees and brush within the work areas. The work...
Notice of Construction – Klondike Park Road Construction
Posted on Thursday, September 21, 2023 02:35 PM
The Town will be completing road work on Klondike Park Road from Judith Court to Watson Avenue. Motorists can expect delays. Roadway will be reduced to one lane of flagged traffic during construction hours from 7:00 a.m. until 6:00 p.m. Roadway surface will be gravel.
Work is scheduled to begin September 20, 2023 and is expected to be completed by October 11, 2023.
Construction activities will include:
- Removal and disposal of asphalt, full width of roadway for approximately 540m.
- Fine grading of...