Beach Drive Construction Update No.8
Posted on Friday, August 15, 2025 03:19 PM
Work Completed This Week
- Storm sewer pipe installation continued on Main Street, and began on Beach Drive
- Dewatering operations continued to improve ground conditions for the storm pipe installation
- Infrastructure Investigation continued throughout the project limits
Working Coming Up Next Week
- Crews will continue with storm sewer pipe installation on Main Street and Beach Drive
- Crews will begin watermain installation on Beach Drive
- Placement of engineered fill will continue on Beach Drive
- Dewatering operations...
Beach Drive Construction Update No.7
Posted on Friday, August 08, 2025 10:59 AM
Work Completed This Week
- Continued removals of existing infrastructure on Beach Drive, including pulverizing the asphalt of Beach Drive from Spruce Street to 2nd Street
- Dewatering operations continue, to improve ground conditions for the storm pipe installation
- Storm sewer pipe installation continued on Main Street
- Commenced engineered fill placement on Beach Drive
- Infrastructure Investigation continued throughout project limits
Working Coming Up Next Week
- Crews will continue with storm sewer pipe...
Beach Drive Construction Update No.6
Posted on Friday, August 01, 2025 09:00 AM
Work Completed This Week
- Continued removals of existing infrastructure on Beach Drive
- The dewatering operations continue to improve ground conditions, for the storm pipe installation
- The crew began storm sewer pipe installation from the storm outlet to Spruce Street
- We removed the existing sheet pile wall along Beach Drive
- Infrastructure Investigation continued throughout project limits
Working Coming Up Next Week
- Continue with removals along Beach Drive
- Dewatering operations will continue to enable...
Beach Drive Construction Update No.5
Posted on Monday, July 28, 2025 02:54 PM
Work Completed This Week
- Installation of hoarding fence was completed along Beach Drive, from Spruce Street to 2nd Street
- Watermain work occurred on Main Street to facilitate upcoming pipe works
- Continued removals of existing infrastructure on Beach Drive Crews have installed floating barriers in the river, designed to manage silt and sediment, at the storm outlet.
- Crews started working on the storm outlet at Spruce Street, to then start installing storm pipe
- The dewatering operations continue to...
Beach Drive Construction Update No.4
Posted on Friday, July 18, 2025 02:18 PM
Work Completed This Week Construction Update
- Continued to install hoarding fence along Beach Drive from Spruce Street to 2nd Street
- We continued to remove existing infrastructure on Main Street, Spruce Street and Beach Drive
- Crews began installing the dewatering system and installed dewatering well points to address ground conditions for the upcoming pipe installation
- We installed wayfinding signage on the fence to help residents and visitors navigate to the beach and local businesses